Traffic Rehabilitation Burgdorf - Oberburg - Hasle b. B., Hasle b. B. Section

The aim of the project is to ease traffic congestion, improve bicycle connections and pedestrian crossings.

The preliminary project consisted of assessing 2 basic options

  • Bypass option:
    Network upgrade with a bypass of the town centre of Hasle b.B. and the necessary accompanying measures
  • Zero+ option:
    Optimisation of the existing road network within the perimeter of Hasle b.B

Main Data

  • Road stretch 1.416 km

Client

Civil Engineering Authority of Bern Canton, OIK IV

Consultant

IUB Engineering AG in consortium

Construction period

2014-2015

Construction costs

Approx. CHF 130 million (both options combined)

Scope of services

  • Preparation of a viability analysis and preliminary project
  • Measures project (action plan)