N04/06 Road Upgrade Schaffhausen Süd - Herblingen
As part of the “bottleneck removal“ programme the N04/06 which is currently operated with two-way traffic will be expanded into a four-lane motorway. The core part of the upgrade is the 1.4 km long Fäsenstaub II Tunnel as well as the two-level road in the cramped inner city of Schaffhausen.
As an alternative to the quick implementation of the upgrade project a safety tunnel will be designed for the existing Fäsenstaub I Tunnel. The project will be developed in close coordination with Schaffhausen municipality and canton as well as respective federal authorities.
Main Data
- Support to the overall project manager with project management, project coordination and administration, process management and controlling
- Technical support in coordination of the subprojects for construction, environment and operating & safety systems with specialist support from ASTRA
- Cost, schedule and quality management in compliance with ASTRA standards
- Financial planning according to ASTRA requirements
Client
ASTRA (Federal Roads Office) Winterthur Branch
Consultant
IUB Engineering AG in consortium
Construction period
2011-2017
Construction costs
CHF 473 million
Scope of services
Owner’s engineering services for the general project upgrading the N04/06 road and for the implementation project for the Fäsenstaub safety tunnel