N02P Gotthard Pass Road, EP Schöllenen (Göschenen-Andermatt)
The Gotthard Pass road has been designated a national road since 2008. With the closure of the Gotthard Road Tunnel (e.g. for the pending rehabilitation of the tunnel) it is potentially the main alternative route for traffic. Therefore, a timely and complete overhaul of the pass is very important. In addition to the actual route and drainage, the measures also include all structures, tunnel, galleries and non-motorised traffic. The historical relevance of the 3rd class national road should also be taken into consideration.
Données principales
- Support to the overall project manager with project management, project coordination and administration, process management, and controlling
- Technical support in coordinating the subprojects for construction, environment and safety & operating systems with specialist ASTRA support
- Cost, schedule and quality management according to ASTRA standards
- Financial planning according to ASTRA guidelines
- Services in procurement, contract management, claim management, invoice control
- Support with public relations work
Maître d'ouvrage
ASTRA (Federal Roads Office) Zofingen Branch
Ingénieurs du projet
IUB Engineering AG
Période
2014-2019
Coûts de construction
CHF 105 million
Prestations
Owner’s engineering services (detailed project - implementation/commissioning) for the overall restoration of the section between Göschenen and Andermatt (approx. 4 km)