K36 Lammschlucht Gorge, Additional Measures 2010

Several structures in the Lammschlucht gorge are in bad condition. To ensure safety (loadbearing safety and serviceability) for road users several structural measures were conducted: natural stone walls, concrete guide walls, concrete road overhangs, concrete supports, concrete bearings, concrete foundations, crash barriers and bridges, joints between concrete elements and concrete guide walls.

Dati principali

  • Sika Mono Top 412 N: 2 t
  • Joint tape: 115 m
  • TM 10 trass cement mortar: 0.5 t

Committente

Lucerne Canton (vif – Transport and Infrastructure Department), Road Inspectorate, Building Section

Progettazione

IUB Engineering AG

Periodo di costruzione

2010

Costi dell'opera

CHF 330,000

Prestazioni

  • Tendering
  • Implementation project
  • Site supervision